Project Details
Based on the performed site visit on 2022-06-23 and the visual inspection carried out, the steel structure supporting the solar panels that need to be installed will be located in a sloped terrain at the edge of the building adjacent to the building generator and outdoor air conditioning units. The steel structure will require steel columns supported on concrete foundations laid on adequate soil layers.
- 2 Inverter (10KW‐48VDC/380VAC ) 3 phase .
- 36 Solar PV panel (540Watt)
- 40 Battery 280amps/12V
- 36 Supporting frame (steel )